Hi Clarke888,
With ore starting to be stockpiled, I thought I'd take a look at the road to production, timing and any risks to that schedule.
From the pic in the presentation released today, log washer, trommel and knelson concentrators appear to be on site and installed - but there was some empty space on the concrete pads. From the production flow sheet in the last quarterly report, the major items seem to be there, but there only needs to be one missing piece.
The last quarterly report which was dated 29 February 2016 stated:
* All major components of the processing plant are either in place on site or are in the final stages of construction and readying for transport to site;
* The new mining plan will see the first gold ore accessed by early April.
Therefore, all seems to be progressing well for gold by early April, but have I missed anything or is there more that you can add?
Also, the pic of the drill rig on the pit floor that you posted from HAV's twitter account, do you know if that is going to drill into the bedrock beneath the current resource? And if so, any guess as to how long before we might see some results?
- Forums
- ASX - By Stock
- HAV
- Road to Production
Road to Production
-
- There are more pages in this discussion • 14 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add HAV (ASX) to my watchlist
(20min delay)
|
|||||
Last
17.0¢ |
Change
0.005(3.03%) |
Mkt cap ! $53.82M |
Open | High | Low | Value | Volume |
16.5¢ | 17.0¢ | 16.5¢ | $11.12K | 66.91K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 70074 | 16.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
17.0¢ | 14871 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
2 | 70074 | 0.165 |
1 | 50000 | 0.160 |
2 | 35612 | 0.155 |
2 | 92208 | 0.150 |
5 | 285663 | 0.145 |
Price($) | Vol. | No. |
---|---|---|
0.170 | 14871 | 1 |
0.175 | 4000 | 1 |
0.190 | 30000 | 2 |
0.200 | 57893 | 2 |
0.210 | 16000 | 1 |
Last trade - 15.07pm 28/03/2024 (20 minute delay) ? |
|
|||||
Last
16.5¢ |
  |
Change
0.005 ( 0.00 %) |
|||
Open | High | Low | Volume | ||
17.0¢ | 17.0¢ | 16.5¢ | 40373 | ||
Last updated 13.26pm 28/03/2024 ? |
Featured News
HAV (ASX) Chart |
The Watchlist
BGD
BARTON GOLD HOLDINGS LIMITED
Alex Scanlon, Managing Director & CEO
Alex Scanlon
Managing Director & CEO
SPONSORED BY The Market Online