january 08 construction report out

  1. 168 Posts.
    very pleasing:

    - The First Ore On Ship (FOOS) date remains at mid May 2008 with overall project completion at 86% measured by value of work.

    - Port works are 90% advanced with a major milestone achieved being the arrival and assembly of the pre-commissioned ship loader which was lifted into place over January 23 - 25.

    - The mine site was 80% complete as at end January with continuing progress on the crushing and screening plants and the product load out vaults.

    -Rail works were 85% complete at end January with the automated track laying complete to chainage 110 and a total of 4 manual track laying teams deployed along the rail line.

    - Project Final Forecast Cost is $2,765 million which is an increase of $66 million from last period. The adjustment was primarily due to an increase in the estimated EPCM costs to WorleyParsons of $61.6m.
 
watchlist Created with Sketch. Add FMG (ASX) to my watchlist
(20min delay)
Last
$10.38
Change
0.010(0.10%)
Mkt cap ! $31.95B
Open High Low Value Volume
$10.38 $10.49 $10.34 $121.6M 11.68M

Buyers (Bids)

No. Vol. Price($)
3 107866 $10.37
 

Sellers (Offers)

Price($) Vol. No.
$10.38 13678 1
View Market Depth
Last trade - 16.10pm 11/12/2019 (20 minute delay) ?
(live)
Last
$10.34
  Change
0.010 ( 0.28 %)
Open High Low Volume
$10.39 $10.49 $10.34 2854163
Last updated 16.00pm 11/12/2019 (live) ?
FMG (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.