Highlights
• Exploration drilling campaign underway with first casing set on Currajong 1
• Seismic program to commence in late July as crew becomes available from current
Perth Basin contract
• Ungani oil lifting and sale completed 8 July
Drilling program
Buru Energy Limited (Buru) advises that subsequent to the spud of the Currajong well on 1
July, the 445mm (17 ½ inch) hole has been drilled to the intermediate casing depth of 715.5
metres measured depth, and 340mm (13 ⅜ inch) casing has been run to 713 metres and
cemented in place. The current operation is preparing to run back in the hole to drill ahead.
The well will be drilled ahead in 311 mm (12 ¼ inch) hole to the prognosed total depth of
2300 metres. This is expected to take approximately two weeks.
Seismic survey program
The seismic contractor for the planned extensive seismic surveys being acquired as part of
the 2021 exploration program, Terrex Pty Ltd, are currently completing surveys for other
operators in the Perth Basin. The Company also received a request from one of the Perth
Basin operators to release the crew to them until the end of July to allow them to complete
an additional program. This request was accommodated by re-ordering some of the planned
Buru operations and will result in a delay to the planned commencement of the Buru program
until late July.
Ungani Oil lifting
The latest lifting of Ungani crude oil from Wyndham
Port was completed today by the MT SCF Pechora for
a total of some 74,000 bbls (gross - Buru’s share
50%).
As per the marketing agreement with BP Singapore Pte
Limited (BP), BP have purchased the crude FOB
Wyndham and will deliver the crude to a refinery in SE
Asia. Under the marketing contract, the price received
will be the actual price BP have sold the crude to the
refinery (being a fixed differential to the average dated
Brent price for the month of July), less shipping and
associated costs. Under these terms Buru’s 50%
revenue share from the lifting is currently estimated at
approximately A$3.2 million, with the price to be
finalised at the end of July.2
Level 2, 16 Ord St West Perth WA 6005 1800 337 330 [email protected] ABN 71 130 651 437
Buru’s Executive Chairman Eric Streitberg commented:
“The first part of the Currajong program has gone according to plan with the rig operating
efficiently and the operation on schedule. We have an exciting few weeks coming up and
are very much looking forward to what Currajong and then Rafael has in store for us.
The oil lifting and sale will also provide a welcome boost to our finances in a climate of
strengthening oil prices with strong global demand.”
- Forums
- ASX - By Stock
- BRU
- Ann: Operations Update
BRU
buru energy limited
Add to My Watchlist
8.33%
!
3.9¢

Ann: Operations Update, page-2
-
- There are more pages in this discussion • 157 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
3.9¢ |
Change
0.003(8.33%) |
Mkt cap ! $28.83M |
Open | High | Low | Value | Volume |
3.8¢ | 3.9¢ | 3.7¢ | $50.77K | 1.346M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 102113 | 3.7¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
3.9¢ | 144765 | 2 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
2 | 102113 | 0.037 |
2 | 1020000 | 0.036 |
2 | 53500 | 0.035 |
1 | 28000 | 0.034 |
4 | 388605 | 0.033 |
Price($) | Vol. | No. |
---|---|---|
0.039 | 144765 | 2 |
0.040 | 963333 | 4 |
0.042 | 17500 | 1 |
0.043 | 150000 | 1 |
0.045 | 125000 | 1 |
Last trade - 14.32pm 26/03/2025 (20 minute delay) ? |
Featured News
BRU (ASX) Chart |
The Watchlist
ATC
ALTECH BATTERIES LTD
Martin Stein, CFO
Martin Stein
CFO
SPONSORED BY The Market Online