Originally posted by ozblue
↑
Some of the fine print is really interesting, and so fine you have to blow the document up to 300-400% to read it!!.
For example, P27,
It states, " The major activities the Company is currently progressing for the process plant include.....
Hazardous area dossier completion"
Then on p29 the table on the bottom, that has to be enlarged a lot to read, is " CuDECO Commissioning High Level Schedule"
First item, "Handover of QA documentation from installer" ........13 Jan 16.
Then later.... Commissioning at 33% throughput (finish) 7th April 16.
Later ......Commissioning at 75% throughput (finish) 7th July 16.
Whatever happened to the January start date and the February full capacity, or for that matter the SAME document that mentions on p80......
"with commercial production expected to commence in January 2016"
SAME document different dates for things to be happening, so yes SB ASIC should reject it outright!!
Expand
Crikey I think you're on to something. I enlarged it by 1000% printed it off, rubbed some vinegar on the top right hand corner then held it over a burning candle for a few seconds and a secret masonic symbol appeared.